Case Studies - Sevenoaks Cycling Route

Sevenoaks Cycling Route

Project Overview

Zack Contractors were contracted to deliver the highways hard landscaping and surfacing works for the East to West Walking, Wheeling & Cycling Route in Sevenoaks Town. Commissioned by Kent County Council and managed by Principal Contractor Amey, the project aimed to create a safer, accessible, and sustainable transport corridor for
pedestrians, cyclists, and wheelchair users.

Client:
Location:
Duration: 
 

Amey on behalf of Kent County Council
Sevenoaks (Various)
18 weeks
 

Project Challenge

The project had a tight programme due to local events, funding constraints, and the need to minimise disruption in a busy urban area. Meeting deadlines without compromising quality or safety was critical. The scope included kerbing, asphalt surfacing, traffic infrastructure works including NAL sockets, inspection chambers and service ducts, traffic signage, road markings, and full traffic management including road closures, diversions, temporary traffic signals with off peak and out of hours working all requiring precise coordination to minimise disruption.

Gallery

Our Approach

01

Comprehensive Planning
Developed a detailed work programme aligned with client deadlines, identifying critical path activities and potential risks.

02

Extended Working Hours
Implemented shifts including early mornings, evenings, and weekends to maximise on-site productivity.

03

Resource Mobilisation
Deployed additional skilled crews and modern plant equipment to accelerate the pace of work without compromising safety or quality.

04

Efficient Materials Management
Pre-planned and coordinated materials deliveries to avoid delays and ensure continuous workflow.

05

Full Traffic Management Provision
Designed and implemented traffic management plans to safely control and divert traffic, protect workers and road users, and minimise disruption to the public.

06

Close Coordination with Streetworks
Worked closely with stakeholder and streetworks teams to schedule and sequence activities, preventing clashes and ensuring smooth progress.

07

Stakeholder Coordination
Maintained close communication with Amey, Kent County Council, local authorities, and emergency services to synchronise traffic management and works.

08

Quality and Compliance

Ensured all kerbing, asphalt surfacing, signage, road markings, and traffic management measures met strict highway and accessibility standards, with thorough inspections and testing.

Outcomes

Through strategic planning and a proactive approach, Zack Contractors successfully completed the Sevenoaks Town East to West route on an accelerated programme. This project now provides a high-quality, safe, and sustainable corridor supporting Kent County Council’s transport and accessibility goals.

Key Achievements

  • Delivered all works ahead of the tight programme, enabling early project handover.

  • Maintained a safe working environment during extended and accelerated work hours with comprehensive traffic management controls.

  • Enhanced route accessibility and safety for all users, including pedestrians, cyclists, and wheelchair users.